Installation of new 13.2KV Armored Cables Parallel
circuits trough cable tray (2,000LF approx).
Installation of 1ea. Master Electrical Room
with 4ea. Double Ended 20,000KW 13.2KV/480V
Metal-Clad Electrical Substation; 1ea. 13.2KV
Switching Units Banks; 2ea. 13.2KV Capacitor
Banks; 1ea. 13.2KV Metal-Clad Switchgear.
Installation of 5ea. Secondary Electrical rooms
with Double Ended 20,000KW 13.2KV/480V Substations
on each room; 8ea. 800amps. MCC’s; 20ea. 1,200amps
MDP’s with all loads
Installation of 1ea. 2,500KW Emergency Generator
TARGET
New power source for HUMIRA Bulk Building.
CONSTRUCTION TIME
The project was perform in 2 years.
PROJECT AMOUNT: $1,500,000
DESCRIPTION
Installation of 3,000 line feet of cable tray
around the plant. Run 100,000 lf of 5kv 500
mcm cable and 2,000 line feet of 4” rigid conduit.
Also installation of cable termination such
as 5kv stresscone.
TARGET
Re-distribution of critical load feeder because
of building demolition.