PROJECT AMOUNT: $ 1,092,081
DESCRIPTION
Some of the work realized in this project were
the installation of VFD’s, Lighting, Grounding,
Feeders to New Control Building, MCC, FA Systems,
Electrical Panelboards and Equipments, Power
to HVAC’s and AHU’s, Pump Control Station, UPS
System, etc.
TARGET
The objective of this project was to perform
the Electrical Upgrade to the following systems:
Brischem Scrubber Area, WWTP, Utilities Area,
MACT Controls, HIRT TOU, TOU-1, Fuel Pumps,
Caustic Pumps, Instrument Air, LEL System, Tray
Deaerator, Utility PLC/LP3 Panel, New Control
Building in 4 phases and DP10.
CONSTRUCTION TIME
The project was perform in 14 months.
We were congratulated by Eng. Juan C. Sanchez
and management from Bristol for our excellent
work and execution of this work, in addition
to a Safety Accident Free during its duration.
|